WEBVTT

00:00:00.000 --> 00:00:02.500
How a dropped kerb is installed: 13 steps, from checking you qualify to council sign-off.

00:00:02.500 --> 00:00:05.300
Step 1 of 13: Check you can have one. Measure the space and check distances from junctions, trees and lamp columns. Each council publishes its own rules.

00:00:05.300 --> 00:00:08.100
Step 2 of 13: Get planning permission if you need it. Usually needed for a new access onto an A, B or classified unnumbered road, or for a flat. Derby: up to 8 weeks.

00:00:08.100 --> 00:00:10.900
Step 3 of 13: Apply to the highway authority and pay its fee. Total council fees in our data: £47 (Bolton) to £875 (Waltham Forest).

00:00:10.900 --> 00:00:13.700
Step 4 of 13: Council survey and decision. Decision times: 2 weeks (Hampshire Fast Track) to 12 weeks (Leicester City).

00:00:13.700 --> 00:00:16.500
Step 5 of 13: Quote and who builds it. Knowsley: contractor contacts you within 7 working days; quote valid 28 days.

00:00:16.500 --> 00:00:19.300
Step 6 of 13: Licence, notice and booking. Usually a section 184 licence. Notice: Knowsley 20 days · BathNES 7 working days · Cheshire East at least 48 hours.

00:00:19.300 --> 00:00:27.300
Step 7 of 13: Traffic management and finding services. The area is fenced off and pipes and cables are located. Essex: covers at least class B125 (BS EN 124).

00:00:27.300 --> 00:00:37.300
Step 8 of 13: Break out and excavate. Old kerbs and footway come up. No single national depth: it is the total of your council's layers.

00:00:37.300 --> 00:00:46.700
Step 9 of 13: Lay the new kerbs. Low kerbs across the opening, a dropper kerb at each end. Cheshire East and BathNES: 25 mm upstand. Knowsley: 5 kerbs, 4.5 m.

00:00:46.700 --> 00:00:53.700
Step 10 of 13: Lay and compact the sub-base. Type 1 sub-base: 150 mm Essex, BathNES · 200 mm Cheshire East · 250 mm Knowsley (asphalt).

00:00:53.700 --> 00:01:00.200
Step 11 of 13: Surfacing, option A (asphalt). Binder 60 mm (BathNES, Cheshire East, Knowsley) to 100 mm (Essex); surface 20 to 25 mm (Essex).

00:01:00.200 --> 00:01:06.700
Step 11 of 13: Surfacing, option B (concrete). Essex and Knowsley: 150 mm C32/40 concrete on a waterproof membrane (special circumstances).

00:01:06.700 --> 00:01:12.700
Step 12 of 13: Let it harden before you drive on it. Knowsley: don't drive across a new crossing for at least 24 hours. Follow your own council's conditions.

00:01:12.700 --> 00:01:17.100
Step 13 of 13: Inspection, sign-off and maintenance period. Maintenance period: 2 years in Devon, Derby, Plymouth and Leicestershire; 24 months Leicester City.

00:01:17.100 --> 00:01:24.500
Step 13 of 13: Inspection, sign-off and maintenance period. Maintenance period: 2 years in Devon, Derby, Plymouth and Leicestershire; 24 months Leicester City.

00:01:24.500 --> 00:01:29.500
Check your council's fees and rules at droppedkerbguide.co.uk