Before any work. The existing footway and full-height kerb. Nothing changes on site until the council has approved the crossing and the contractor holds any licence or permit it needs.
Signing and finding services. Barriers and signs go up around the work area. Utility apparatus under the footway (pipes, cables, ducts) is located before digging; its depth varies, so it has to be found on site. Essex says any utility covers within a residential crossing must be at least class B125 (BS EN 124).
Breaking out and excavating. The old kerbs and footway are removed and the ground is dug out to the depth the council's specification needs for the new layers. Cheshire East says existing kerbs fit for re-use are taken up and stacked on site.
New kerbs on a concrete bed. Low crossing kerbs go in across the opening, with tapered dropper kerbs either side, bedded and backed in concrete. Cheshire East and BathNES both require a 25 mm upstand above the road channel. Cheshire East: ST1 concrete bed 150 mm thick by 300 mm wide, backing 150 mm thick up to 50 mm from the kerb top. BathNES: C6/8 or ST1 bed at least 125 mm thick and 375 mm wide.
Sub-base. Type 1 unbound granular sub-base (MCHW clause 803) is laid and compacted. Thickness for a residential crossing: 150 mm (Essex, BathNES), 200 mm (Cheshire East), 250 mm (Knowsley, asphalt). Cheshire East says it's compacted in layers of no more than 100 mm.
Surfacing. Asphalt: binder course 60 mm (BathNES, Cheshire East, Knowsley) to 100 mm (Essex), then surface course 20 mm (BathNES, Cheshire East, Knowsley) to 25 mm (Essex). Concrete (Essex and Knowsley, usually only to extend an existing concrete crossing): 150 mm C32/40 concrete on a waterproof membrane, brush-textured finish.
Finished, then inspected. The crossing falls from the back of the footway to the kerb: Cheshire East asks for 1 in 16 where practicable and no steeper than 1 in 12; Essex and Knowsley 1 in 15 desired, 1 in 12 absolute maximum; BathNES a maximum of 1 in 14. Knowsley advises not driving over a new crossing for at least 24 hours. The council then inspects it.
Diagram by Dropped Kerb Guide. Figures are examples from named council specifications; check your own council's.