In short. This page is about how a dropped kerb is built on site, after your council has approved the application: break out, excavate, new kerbs on concrete, sub-base, surfacing, then inspection. For how to apply, see how to get a dropped kerb. For prices, see dropped kerb cost. There is no national construction standard. Every highway authority publishes its own specification, so the depths and materials below are examples from four named councils, not a rule for yours.
Measure the space where you would park, and check the distance from junctions, trees, lamp columns and other street furniture. Councils publish minimum depths and siting rules: see dropped kerb rules or try the 2-minute eligibility checker. If you pave the front garden, the 5 square metre permeable surface rule applies in England.
2. Get planning permission if you need it
A new access onto an A, B or classified unnumbered road, or a crossing for a flat, usually needs planning permission as well as the council's highway consent. See do you need planning permission? and is my road classified? Derby says a planning decision can take up to 8 weeks.
3. Apply to the highway authority and pay its fee
Apply to the council that looks after the road (in two-tier areas of England, the county). Total council fees in our data run from £47 (Bolton) to £875 (Waltham Forest); application fees alone from £25.50 (Middlesbrough) to £660 (Hammersmith and Fulham). Find yours with the council finder or the fee table, and see how to apply.
4. Council survey and decision
An inspector checks the site: visibility, gradients, drainage, trees, street furniture and apparatus in the footway. Published decision times vary widely, from 2 weeks (Hampshire Fast Track) to 12 weeks (Leicester City). See the full list on how long a dropped kerb takes.
5. Quote and who builds it
Depending on your council, the council builds it, you choose from its approved list, or you can use any suitably qualified contractor. See who builds a dropped kerb. Knowsley, for example, says its contractor will contact you within 7 working days to arrange a site visit, and the quote it sends is valid for 28 days. If you can choose, see what a contractor should have.
On site, stage by stage
Scroll through the steps and the cross-section updates. The text of each step and the caption under the diagram say the same thing as the picture.
Surface:
Before any work. The existing footway and full-height kerb. Nothing changes on site until the council has approved the crossing and the contractor holds any licence or permit it needs.
Signing and finding services. Barriers and signs go up around the work area. Utility apparatus under the footway (pipes, cables, ducts) is located before digging; its depth varies, so it has to be found on site. Essex says any utility covers within a residential crossing must be at least class B125 (BS EN 124).
Breaking out and excavating. The old kerbs and footway are removed and the ground is dug out to the depth the council's specification needs for the new layers. Cheshire East says existing kerbs fit for re-use are taken up and stacked on site.
New kerbs on a concrete bed. Low crossing kerbs go in across the opening, with tapered dropper kerbs either side, bedded and backed in concrete. Cheshire East and BathNES both require a 25 mm upstand above the road channel. Cheshire East: ST1 concrete bed 150 mm thick by 300 mm wide, backing 150 mm thick up to 50 mm from the kerb top. BathNES: C6/8 or ST1 bed at least 125 mm thick and 375 mm wide.
Sub-base. Type 1 unbound granular sub-base (MCHW clause 803) is laid and compacted. Thickness for a residential crossing: 150 mm (Essex, BathNES), 200 mm (Cheshire East), 250 mm (Knowsley, asphalt). Cheshire East says it's compacted in layers of no more than 100 mm.
Surfacing. Asphalt: binder course 60 mm (BathNES, Cheshire East, Knowsley) to 100 mm (Essex), then surface course 20 mm (BathNES, Cheshire East, Knowsley) to 25 mm (Essex). Concrete (Essex and Knowsley, usually only to extend an existing concrete crossing): 150 mm C32/40 concrete on a waterproof membrane, brush-textured finish.
Finished, then inspected. The crossing falls from the back of the footway to the kerb: Cheshire East asks for 1 in 16 where practicable and no steeper than 1 in 12; Essex and Knowsley 1 in 15 desired, 1 in 12 absolute maximum; BathNES a maximum of 1 in 14. Knowsley advises not driving over a new crossing for at least 24 hours. The council then inspects it.
6. Licence, notice and booking
Stage 1 of 7: Before any work.
Approval is usually given under section 184 of the Highways Act 1980. If your own contractor builds it, they may also need a licence and must book the works on the street works register. Supervisors and operatives need street works qualifications (NRSWA 1991 s67). Published notice periods: Knowsley 20 days, Staffordshire 20 days, Edinburgh 10 working days, BathNES 7 working days to its engineer, Cheshire East at least 48 hours before work starts. More on section 184 licences and street works.
7. Traffic management and finding services
Stage 2 of 7: Signing and finding services.
On the day, the work area is fenced off with barriers and signs, and the crew locates utility pipes and cables before digging. Covers inside a crossing may need upgrading: Essex says statutory undertakers' covers in a residential crossing must be at least class B125 to BS EN 124. Moving apparatus is arranged with the utility company and can add cost and time.
8. Break out and excavate
Stage 3 of 7: Breaking out and excavating.
The full-height kerbs and the footway are taken up and the ground is dug out to the depth the specification needs. There's no single national depth: it's the total of your council's layers (see the specification table). Cheshire East says kerbs fit for re-use are stacked on site.
9. Lay the new kerbs
Stage 4 of 7: New kerbs on a concrete bed.
Low crossing kerbs are laid across the opening with a tapered dropper kerb at each end. BathNES describes a standard single access as 4 dropped kerbs and 2 dropper kerbs; Knowsley as 5 kerbs, 4.5 m in total: a 0.9 m taper each end and three low kerbs. Both Cheshire East and BathNES require a 25 mm upstand above the road channel, with the kerbs bedded and backed in concrete (see the table below). Precast kerbs are to BS EN 1340 (BathNES, Knowsley). An edging goes along the back of the crossing. For the kerb codes (BN, HB2, DL1/DR1) and sizes, see kerb types for a dropped kerb.
10. Lay and compact the sub-base
Stage 5 of 7: Sub-base.
Type 1 granular sub-base is spread and compacted. Residential thicknesses in the specs we checked: 150 mm (Essex, BathNES), 200 mm (Cheshire East) and 250 mm (Knowsley, asphalt crossing). Cheshire East requires layers no thicker than 100 mm, compacted with plant giving at least 1 tonne of effective force. Essex and Knowsley say more sub-base is needed if ground conditions are poor.
11. Surface it: asphalt or concrete
Stage 6 of 7 (asphalt): Surfacing.Stage 6 of 7 (concrete): Surfacing.
Most specs we checked use asphalt: a binder course, then a thinner surface course. Essex and Knowsley also give a concrete specification for residential crossings (150 mm C32/40 on a waterproof membrane), but say it's for extending an existing concrete crossing or special circumstances. Use the toggle on the diagram to compare.
12. Let it harden before you drive on it
Stage 7 of 7 (asphalt): Finished, then inspected.
Knowsley advises not driving across a new crossing for at least 24 hours so the concrete and tarmac can harden. Other councils set their own conditions, so follow the advice on your approval and from whoever built it.
13. Inspection, sign-off and maintenance period
Stage 7 of 7 (asphalt): Finished, then inspected.
The council inspects the finished crossing. If your own contractor built it, you may be responsible for defects for a maintenance period: 2 years in Devon, Derby, Plymouth and Leicestershire, 24 months in Leicester City. Keep the paperwork.
How long each stage takes
Councils publish their own timescales. Ranges here come from council websites in our data; see the full timeline guide for every council we've checked.
Stage
Published examples
Planning permission (if needed)
Up to 8 weeks (Derby); Leicestershire warns it can take over 8 weeks
Council decision
2 weeks (Hampshire Fast Track) to 12 weeks (Leicester City)
Notice before work starts
48 hours (Cheshire East) to 20 days (Knowsley, Staffordshire)
Wait for a council-built crossing
Within 28 working days of payment (Knowsley) to at least 16 weeks (Birmingham)
Building work on site
1 to 2 days (Leicestershire); normally within 3 days (Derbyshire). BathNES asks to be told in writing if work will take longer than 7 working days.
Before driving on it
At least 24 hours advised (Knowsley)
Maintenance period (own contractor)
2 years (Devon, Derby, Plymouth, Leicestershire); 24 months (Leicester City)
Construction specs compared: four councils
These are the residential (domestic) specifications each council publishes for contractors. They're similar in shape but differ in the numbers, which is why you should always use your own council's document. Commercial and industrial crossings are thicker.
Residential vehicle crossing specifications, as published by each council. Checked 12 October 2026.
C6/8 or ST1 bed ≥125 × 375 mm; backing 150 mm; 25 mm upstand
1:14 max
Type 1 sub-base and concrete mixes such as ST1 are defined in the Manual of Contract Documents for Highway Works (MCHW), Specification for Highway Works, which these councils cite (clause 803 for Type 1). Asphalt layers are to BS EN 13108 (Essex, Knowsley, BathNES); Cheshire East's 2019 document still cites BS 4987.
Tarmac, concrete, block paving or resin: who chooses the surface?
The crossing itself, the part across the pavement or verge, becomes part of the public highway, so the highway authority decides what it's surfaced with. You can't simply pick the same finish as your driveway. Council rules differ:
Tarmac only:Worcestershire says it will "only allow tarmac on the highway due to potential future repairs", and requests for block paving or slabbing will not be allowed.
Council's choice, usually matching the street:Shropshire says a dropped kerb will be built of tarmac, concrete or block paving at the highway authority's discretion, generally similar to other dropped kerbs in the road. Rhondda Cynon Taf says crossovers will generally be tarmac or block paving to match the existing footway, and in keeping with the footway in a conservation area.
Several standard finishes:Knowsley lists bitmac (tarmac), concrete paving flags, block paving or concrete, with other materials such as setts in conservation areas. The council's highway officers decide the finish.
Concrete as the exception: Essex and Knowsley publish a concrete specification (see the table above) but say it's for extending an existing concrete crossing or special circumstances.
Resin: none of the council documents cited on this page lists resin as a finish for the crossing. If you want resin, use it on your own driveway and expect the crossing to be finished in whatever the council specifies.
Your driveway is different. The surface behind the boundary is your choice, but in England a new or replacement front garden hard surface over 5 square metres needs planning permission unless it's permeable or drains onto your own land. See paving a front garden and permeable driveways. Shropshire, for example, says no permission is needed for a driveway of any size using permeable surfacing such as gravel, permeable block paving or porous asphalt, or where rainwater runs to a lawn or border.
We haven't found council figures comparing tarmac and concrete prices for a crossing, so we don't give one. See dropped kerb cost for the build prices councils do publish.
Pedestrian dropped kerbs are different
A dropped kerb at a pedestrian crossing point is designed to different rules. The Department for Transport's tactile paving guidance says its base should preferably be flush with the road, with a maximum upstand of 6 mm with a rounded bullnose, a ramp no steeper than 1 in 12 (1 in 20 where space allows) and dropper kerbs no steeper than 1 in 11. Don't use those figures for a driveway crossing, or the vehicle-crossing ones for a pedestrian crossing.
Embed this video and diagram
You can embed the installation video and the step-by-step cross-section on your own website for free, for example on a council, contractor, college or forum page. Please keep the credit link. Copy and paste:
<iframe src="https://www.droppedkerbguide.co.uk/embed/dropped-kerb-installation" title="How a dropped kerb is installed: step-by-step cross-section" width="100%" height="980" loading="lazy" style="border:0;max-width:900px"></iframe>
<p>Diagram: <a href="https://www.droppedkerbguide.co.uk/how-a-dropped-kerb-is-installed">How a dropped kerb is installed</a> by Dropped Kerb Guide</p>
There's no national depth. It's the total of the layers in your council's specification. For example, Essex's residential asphalt crossing is 150 mm of sub-base, 100 mm of binder and 25 mm of surface; BathNES is 150 mm, 60 mm and 20 mm.
What concrete is used for a dropped kerb?
Kerbs are bedded and backed in a low-strength concrete: ST1 in Cheshire East, C6/8 or ST1 in BathNES. Where Essex or Knowsley allow a concrete crossing surface, it's 150 mm of C32/40 concrete on a waterproof membrane for a residential crossing.
How high is the kerb on a dropped kerb?
Cheshire East and BathNES both specify a 25 mm upstand above the road channel at a vehicle crossing. Pedestrian crossing points are different: DfT guidance allows 0 to 6 mm with a rounded bullnose.
How long does it take to build a dropped kerb?
The building work is usually short (Derbyshire says normally within 3 days; Leicestershire 1 to 2 days), but the approval, quote and booking before it typically take weeks or months. See our timeline guide.
Can I have block paving or resin on my dropped kerb?
Only if your council allows it, because the crossing is part of the public highway. Worcestershire allows tarmac only; Shropshire, Rhondda Cynon Taf and Knowsley may use block paving, usually to match the footway, at the council's discretion. None of the council documents we cite lists resin for the crossing.
Is a dropped kerb tarmac or concrete?
Usually tarmac (asphalt) in the specifications we checked. Essex and Knowsley allow a concrete surface, mainly to extend an existing concrete crossing. Your council decides.
When can I drive on a new dropped kerb?
Follow your council's or contractor's advice. Knowsley, for example, advises not driving over a new crossing for at least 24 hours.