Dropped Kerb Guide

West Berkshire Council dropped kerbs: fee, who builds it and how to apply

West Berkshire Council charges £202 to apply for a dropped kerb (£551 in total council fees); building the crossing is extra. Source: West Berkshire Council website, checked 4 October 2026. Everything you need to apply for a dropped kerb (vehicle crossing) with West Berkshire Council, from the council's own website.

Last reviewed: Page updated: Edited by our editor

Homeowner application fee£202Fee shown on West Berkshire's pages on 4 Oct 2026
Total council fees£551Application fee plus other published council fees. Building it costs extra.
Who builds itAny qualified contractorYour own qualified contractor
Decision timeUp to 6 weeks
Permission valid forNot published

West Berkshire: Dropped kerbs (vehicle access)

What our FOI request found

Calendar years 2023 to 2025.

89.5%

89.5% of decided applications were approved
239 approved and 28 refused, 2023-25

  • Applications received2962023: 74 · 2024: 112 · 2025: 110
  • Approved239of 267 decided
  • Refused2810.5% of decided
  • Decision timeabout 54-63 calendar days (2024-25)as reported by the council
YearReceivedApprovedRefusedRefusal rate
2023745969%
2024112941413%
20251108688%

Refusal rate 10.5% of decided applications (2023-25 calendar), ranked 56 of 101 councils (1 = lowest refusal rate) using the same method as our refusal rates by council.

West Berkshire approved 89.5% of decided applications, about the same as the 89% across all 101 councils that have sent us usable figures so far. Councils count and record applications differently, so treat this as a rough guide, not a league table.

Why applications get refused here

  • Send complete information: incomplete applications were a reason in 2023 and 2024.
  • Check whether planning permission is required.
  • Make sure the forecourt depth and parking layout meet the design rules.
  • Highway safety near junctions, lay-bys and trees is a reason in 2025.

Source: Freedom of Information response from West Berkshire Council, ref FoI/2026/1324, 20 October 2026. Figures only; the council's documents are not published here. Re-used under the Open Government Licence.

Applying to West Berkshire? Our free dropped kerb templates include a landlord consent letter, a site plan grid and an application checklist.

Not to be confused with. West Berkshire Council doesn't cover every address nearby. These councils are separate highway authorities, with their own fees and rules: Reading Borough Council. Check your postcode.

Who builds dropped kerbs in West Berkshire?

In West Berkshire you need the council's consent under section 184 of the Highways Act 1980 before building a vehicle access. You appoint a private contractor, who must hold £5m public liability insurance, use operatives and supervisors accredited under the New Roads and Street Works Act 1991, and obtain a Section 171 licence to excavate the highway.

How much does a dropped kerb cost in West Berkshire?

Homeowner application fee: £202. Covers the site inspection and issue of the licence; payment is requested online once your application is approved. Fee correct as of 1 April 2026.

Section 171 licence to excavate the highway (your contractor applies): £349

Total council fees: £551 (construction not included).

Building it: West Berkshire doesn't publish a construction price. See typical build prices from councils that do.

Estimate your total for West Berkshire with the calculator

West Berkshire's total council fees are above the UK median of £250 across the 170 councils in our Dropped Kerb Fee Index 2026. For build prices and what pushes them up, read how much a dropped kerb costs.

Contractor requirements in West Berkshire

  • Public liability insurance of £5m (application pack); the Section 171 licence application asks for a certificate of at least £10 million
  • Operatives and supervisors accredited under the New Roads and Street Works Act 1991
  • Obtains a Section 171 licence to excavate the highway (£349)
  • Checks for public utility apparatus that may need moving or protecting

How to check street works cards and insurance before you hire: our guide to dropped kerb contractors.

How to apply in West Berkshire

  1. On a classified (A, B or C) road, get planning consent first; on an unclassified road you don't need it.
  2. Email the application form with a detailed sketch of the proposed access to West Berkshire's highways asset management team.
  3. An officer visits for a technical assessment; if approved, you're asked to pay £202 online.
  4. Your contractor gets a Section 171 licence (£349); give the council 10 days' notice before work starts on the highway.
  5. When the work is satisfactory, West Berkshire issues a Letter of Consent.

Before you apply, check whether you need planning permission: it mostly depends on whether your road is classified. Then use our step-by-step dropped kerb application guide alongside West Berkshire's own steps above.

How long does a dropped kerb take in West Berkshire?

  • Allow up to 6 weeks for an application to be processed.
  • 10 days' notice before work starts on the public highway.

Size and siting rules

  • Parking at least 2.4m wide and 4.8m deep (5.5m in front of a garage).
  • Sight lines measured 2.4 metres back from the carriageway edge: 43m each way at 30mph, 25m at 20mph.

These sit alongside the general dropped kerb rules. Every crossing in West Berkshire needs the highway authority's consent under section 184 of the Highways Act 1980, and the council can act if a kerb is crossed or a crossing built without it: see the law on dropped kerbs.

Planning permission and extending a dropped kerb in West Berkshire

Do I need planning permission for a dropped kerb in West Berkshire? Possibly. West Berkshire's guidance says: On a classified (A, B or C) road, get planning consent first; on an unclassified road you don't need it. Planning permission is separate from the dropped kerb permission. Planning permission guide.

Can I extend my dropped kerb in West Berkshire? Yes, but only with West Berkshire's permission, as for a new crossing. West Berkshire doesn't publish separate rules or a fee for extensions. Widening guide.

Good to know

  • Work done under a Road Opening Licence is covered by the contractor for a maintenance period of 2 years.
  • If the access fails the council's standards and isn't put right within 28 days, the council can do the repairs and recover its costs.

No driveway but want to charge an electric car? Read about EV cable channels.

Free templates for your West Berkshire application

More templates

All free templates

Ready to apply in West Berkshire?

Check your property qualifies and have everything ready, then apply on the council's own website.

West Berkshire: Dropped kerbs (vehicle access) Eligibility checker Printable checklist

Don’t want to do the paperwork? West Berkshire application drawings, £129 (1:200 site plan + form answers; we submit where your council allows; council fees separate; cancel within 14 days).

Areas covered

Main towns: Newbury, Thatcham, Hungerford, Burghfield Common, Theale, Mortimer, Lambourn and Pangbourne, plus smaller places nearby.

Source: ONS Open Geography Portal, built-up areas (2022), largest first. Homes near a boundary can be in a neighbouring council, so check your postcode if you're not sure.

Nearby councils

Dropped kerb guides